147th Avenue, Baltimore Street and 148th Lane Reconstruction from Aberdeen Street to Hastings Street

Lead Engineer: Jessie Kolar EIT
E-mail: jkolar@rfcengineering.com
(763) 862 - 8000

Approved Plans
Schedule


10/26/18: Paving was completed.

10/17/18: Curb is scheduled to begin 10/17/18

8/22/18: Resident notice mailed out regarding Start of Construction Construction Notice.

6/19/18: Ham Lake City Council accepted the Street Reconstruction project. The low bidder is Douglas-Kerr Underground, LLC. A project schedule will be posted when available.

2/7/18: The Contractor is scheduled to begin tree removal on Monday 2/12.

2/2/18: Surveyors will be on site marking trees and staking/flagging areas to be cleared on Monday, February 5th. The contractor plans to begin tree clearing work on Wednesday, February 7th. A resident notice was sent out today which can also be viewed by clicking Resident Notice.

The tree removal plans can be viewed at Tree Removal Plans.

Tree removal will be completed between February 12th and March 31st. Stump removal will be completed by May 31st.

Reconstruction is scheduled to commence in 2018.



 

 
The above information will be maintained as up to date as possible.