0912 - Aberdeen Street from 144th Avenue to 145th Avenue

Lead Engineer: Cindy Adriaens, Project Engineer
E-mail: cadriaens@rfcengineering.com
(763) 862 - 8000

The General Contractor is North Pine Aggregate and the contacts are:

Brent Jensen 612-770-6681
Keith Herman 612-290-0157

6/9/20: Site grading is underway north of 144th Avenue. Grading will continue for the next 5 weeks with trucks hauling in and out intermittently during this time. Removals are scheduled for the second week in July, storm sewer is scheduled to begin mid-August and paving is scheduled to begin in September.

6/1/2020: Clearing and grubbing is underway. Silt lfence is completed. Sign, mailbox, culverts, bituminous and curbing removals to begin soon.

2/3/20: North Pine Aggregate, Inc. was awarded the bid for the construction project.

1/15/20: Bids will be opened at 10:00am.

12/17/19: Advertisement for Bids were advertised in Star Tribune and on QuestCDN.com.

12/16/19: City Council approved plans and authorized the advertisement for bids.






Notice To Contractors

Download Plans Last Updated on 3/4/2020 11:01:44 AM

Planholders List      Last Updated on 1/14/2020 11:29:15 AM

Bid Results