155th Avenue from Naples Street to Lexington Avenue upgrade

Lead Engineer: John Youngblood, P.E.
E-mail: jyoungblood@rfcengineering.com
(763) 862 - 8000

Contractor contact information:
Dresel Contracting
Josh Dresel, President; Office: (651) 257-9469 Cell: (651) 328-1470

9/4/19: The City Council awarded the project to Dresel Contracting

8/29/19: Bids will be opened at 10:00am.

8/8/19: Advertisement for Bids were advertised in Star Tribune and on QuestCDN.com.

2/14/19: Surveyors will be on site marking trees and staking/flagging areas to be cleared on Monday, February 18th. The contractor could begin tree clearing work as early as Tuesday, February 19th. A resident notice was sent out today which can also be viewed by clicking Resident Notice.

The tree removal plans can be viewed at Tree Removal Plans.

Tree removal will be completed between February 19th and March 31st. Stump removal will be completed by May 31st.

11/5/18: Construction is scheduled to commence in 2019.