0922 - MSA Eveleth Street Construction from 134th Avenue to Bunker Lake Boulevard

Lead Engineer: Tom Collins, P.E.
E-mail: tcollins@rfcengineering.com
(763) 862 - 8000


All project work is scheduled to be completed by 9/30/17.

The Prime Contractor is Astech and the contact is:
Phil Johnson - Estimator - 320-248-3108
E-mail: astechphil@outlook.com

10/31/16: Construction is complete and traffic control is removed on Bunker Lake Boulevard. The lane striping and sign installation on Bunker Lake Boulevard will be completed this week with minimal traffic interruption. Other than minor items that will not affect traffic or properties, the project is complete.

10/19/16: Paving the turn lanes on Bunker Lake Boulevard will begin on Friday, October 21st. The concrete median will be completed on Tuesday, October 25th. The wearing course paving for Eveleth Street will be completed on Wednesday, October 26th.

10/3/16: Removals are currently underway on Bunker Lake Boulevard and will be completed this week as well as curb, gutter and median placement. Paving is scheduled to be completed next week.

9/20/16: Paving is nearing completion with the final lift of bituminous scheduled for 2017.

8/31/16: Curb placement is complete and roadbed preparation for asphalt is scheduled to begin the week of September 6th and continue for several weeks.

8/23/16: The road preparation is complete for curb placement.

8/10/16: The storm sewer installation is complete.

7/5/16: ASTECH hand delivered the project schedule, which can be linked to from the below hyperlink.

6/15/16: The pre-construction conference will take place at City Hall to discuss the project scope, utility relocations, schedule, permits, inspection notification and safety requirements.

4/4/16: The City Council awarded the project to Asphalt Surface Technologies Inc. (ASTECH).

2/16/16: Bids will be opened on 3/29/16 and project award is anticipated at the 4/4/16 Council meeting.

10/21/14: Survey is complete. Design of the project will commence and continue through winter.

9/25/14: Notices were sent to residents summarizing the proposed street section, utility markings, survey and schedule.

Approved Plans

Schedule




 

 