1505 - Aberdeen Street reconstruction between Constance Boulevard and 165th Avenue

Lead Engineer: Tom Collins, P.E.
E-mail: tcollins@rfcengineering.com
(763) 862 - 8000

All project work is scheduled to be completed by 11/11/17.

The Prime Contractor is Midwest Civil Constructors and the contact is:
Matt Thompson - President - (612) 669-8635
E-mail: matt@midwestcivilconstructors.com

10/21/16: Concrete curb and gutter is scheduled to be placed Tuesday October 25th. Construction is on schedule to be completed early November.

9/29/16: Construction will begin October 4th. Mailboxes will temporarily be relocated to the intersection of Aberdeen Street and 165th Avenue.

8/24/16: Property owner notifications sent out, which included the Contractor start date as early as 9/12.

7/18/16: The City Council awarded the project to Midwest Civil Constructors.

6/13/16: Advertisment for bids starts this week and bids will be opened July 13th.

5/14/15: Survey notifications mailed to property owners. Survey and wetland delineation required by the Coon Creek Watershed District will be completed in June. Design will be completed during the fall of 2015 with construction in 2016.

3/31/15: Notification was received from the DNR that impacts to protected state-listed plants was not anticipated because of lack of habitat.

Approved Plans

Schedule



 

 
The above information will be maintained as up to date as possible.