1602.055/1702.034 - County Ditch Culvert Installations at 155th Avenue and at Naples Street

Lead Engineer : Tom Collins P.E.
(763) 862 - 8000


8/29/17: The culvert replacement start date has been delayed to Tuesday, September 5th. A resident notice was sent out last week which can also be viewed by clicking Resident Notice

Road closures will take place during culvert work, possible detour routes can be viewed by clicking 155th Ave Naple St

9/18/17: The culvert replacements have been completed and the Naples street culvert ROW has been seeded. The 155th Ave culvert ROW will be seeded soon.




 

 
The above information will be maintained as up to date as possible.