167th Avenue, Fraizer Street and 165th Avenue Street Construction

Lead Engineer: Jessie Kolar EIT
E-mail: jkolar@rfcengineering.com
Office: (763) 862 - 8000


The Prime Contractor is Asphalt Surface Technologies (ASTECH) and the contact is:

Lance Bemboom - Project Superintendent
Office: (320) 363-8500
Mobile: (320) 248-7720

Approved Plans
Schedule

6/12/19: The second lift of asphalt is scheduled to be completed in late July. The website will be updated with the exact dates closer to the day.

6/12/19: Seeding is scheduled to be completed in the next week. There has been issues contacting the subcontractor to complete this work.

5/16/19: Paving is scheduled for tomorrow, 5/17/19, weather permitting.

5/8/19: Driveway culverts are being placed tomorrow 5/9/19, roadway paving is scheduled for the week of May 13th. Additional information to come.

5/1/19: Spring construction is anticipated to begin May 6th, weather permitting.

11/13/18: Paving is postponed until 2019. Contractor will complete temporary mulching of disturbed areas and ramping driveways this week or early next week.

11/8/18: Roadway paving scheduled for November 12th and 13th. Driveway paving scheduled for November 14th.

11/7/18: Paving scheduled for week of November 12th.

10/29/18: Final grading finishing up this week. Paving anticipated to be done November 7th.

10/17/18: Concrete spillways and driveways were poured.

10/16/18: Concrete curb and gutter was poured.

7/25/18: Property owner notifications mailed out.

7/25/18: Tree clearing is scheduled to begin July 30th.

6/11/18: The Contractor anticipates that construction will commence in late July or early August.

6/4/18: The City Council awarded the project to ASTECH.

5/31/18: Bids will be opened at 11:00 am.

5/10/18: The advertisement for bids posted in the Star Tribune.

5/7/18: City Council approves plans and authorizes the advertisement for bids.











 

 
The above information will be maintained as up to date as possible.