Approved Plans
Schedule

11/8/18: Roadway paving scheduled for November 12th and 13th. Driveway paving scheduled for November 14th.

11/7/18: Paving scheduled for week of November 12th.

10/29/18: Final grading finishing up this week. Paving anticipated to be done November 7th.

10/17/18: Concrete spillways and driveways were poured.

10/16/18: Concrete curb and gutter was poured.

7/25/18: Property owner notifications mailed out.

7/25/18: Tree clearing is scheduled to begin July 30th.

6/11/18: The Contractor anticipates that construction will commence in late July or early August.

6/4/18: The City Council awarded the project to ASTECH.

5/31/18: Bids will be opened at 11:00 am.

5/10/18: The advertisement for bids posted in the Star Tribune.

5/7/18: City Council approves plans and authorizes the advertisement for bids.











 

 