167th Avenue, Fraizer Street and 165th Avenue Street Construction

Lead Engineer: Jessie Kolar EIT
E-mail: jkolar@rfcengineering.com
Office: (763) 862 - 8000


The Prime Contractor is Asphalt Surface Technologies (ASTECH) and the contact is:

Lance Bemboom - Project Superintendent
Office: (320) 363-8500
Mobile: (320) 248-7720

Approved Plans
Schedule


7/25/18: Property owner notifications mailed out.

7/25/18: Tree clearing is scheduled to begin July 30th.

6/11/18: The Contractor anticipates that construction will commence in late July or early August.

6/4/18: The City Council awarded the project to ASTECH.

5/31/18: Bids will be opened at 11:00 am.

5/10/18: The advertisement for bids posted in the Star Tribune.

5/7/18: City Council approves plans and authorizes the advertisement for bids.











 

 
The above information will be maintained as up to date as possible.