1802.054 - University Avenue Reconstruction from Andover Boulevard to 157th Avenue

Project Engineer : Cynthia Adriaens
CAdriaens@rfcengineering.com
(763) 862 - 8000

Contractor Information: North Valley, Inc.
Project Manager - Matt Echols
matt@northvalleyinc.net
(612) 282-6270

Curb and Gutter Construction Notice
Approved Plans
Construction Schedule
Resident Notice

5/13/19
Concrete curb and gutter construction will begin on the east side of University Avenue.

4/30/19
Temporary mailboxes will be placed near original location.

4/29/19
Traffic signs will be placed and construction will begin.

4/22/19
Resident Notices mailed out




 

 