0812 - Sunrise Addition Street Reconstruction
Lead Engineer : Tom Collins P.E.
(763) 862 - 8000


April 7, 2011
Inlet protection will again be placed in the catch basins since Turf has not been established.

November 4, 2010
Inlet proection will be removed to prevent ice dams as most turf is now covered with snow.




 

 