2109 - Tippecanoe Street Reconstruction S of Constance Boulevard
Lead Engineer : David A. Krugler, P.E.
E-mail: dkrugler@rfcengineering.com
(763) 862 - 8000

8/14/23 - The City of Ham Lake sent notices to residents on Sept 26, 2022 detailing the suspension of the project.
The City will re-route traffic to the new section of roadway when the Contractor installs the top lift of asphalt to prevent damage to the new roadway.

5/15/23 - Construction has been suspended per Sept 26, 2022 Ham Lake City Council Budget Meeting. Notices

8/8/22 - Construction will not commence until Spring 2023.

6/16/22 - Notices have been sent out via mail to inform residents of updated project timelines.

3/11/22 - Rivard Construction will be performing the tree clearing portion of the road construction project due to the Ham Lake Oak Wilt requirement that no oak trees are to be removed between April 1st and July 15th.

Mike Rivard - (763) 753-7888
(612) 919-5680(cell)
Tree Clearing Resident Notice
Approved Tree Clearing Plans




 

 
The above information will be maintained as up to date as possible.