2302.038 - County Ditch #58 - 152nd Avenue Cross Culvert
Lead Engineer : David Krugler P.E.
E-mail: dkrugler@rfcengineering.com
(763) 862 - 8000

8/30/24 - The road is open for use. The only remaining work item is turf establishment.

8/22/24 - The site has been paved. Once the boulevards have been graded and seeded the roadway will be opened.

8/21/24 - Paving has been rescheduled for today. Both lifts of pavement will be installed by the end of the day.

8/19/24 - Paving of the first lift is planned for Thursday 8/22/24, weather depending.

8/19/24 - Grading of the ditch and roadway is complete. Paving the roadway is the next step, however a paving date has not been determined yet.

8/8/24 - Subgrade preparation and installation of Class 5 is in progress and will be completed by the end of the day.

8/6/24 - Ditch regrading and seeding has been completed. Grading and aggregate installation of the roadway will begin once the road base dries out.

8/1/24 - Rip rap has been installed on both ends of the box culvert. Grading of the roadway will resume once the site has had a chance to dry out.

7/31/24 - The temporary bypass pipe is being removed and the creek will be realigned back into the box culvert. Grading of the ditch and roadway is progressing.

7/26/24 - The box culvert has been fully installed. Backfilling around the box culvert is currently happening.

7/25/24 - The box culvert is being installed today.

7/24/24 - The aggregate bedding for the box culvert is being installed today. Installation of the box culvert sections will begin Thursday 7/25/24.

7/22/24 - The creek is now low enough to remove the existing culverts. The creek will temporarily be bypassed to the east side of the project. The box culvert sections will start arriving on site Thursday 7/25/24 at the earliest.

7/11/24 - The creek bypass pipe was installed on 7/10/24. The creek's water level needs to come down a few more inches before the creek can be temporarily diverted.

7/1/24 - The creek's water level is still too high to remove the existing pipe and temporarily divert the creek around the construction area.

6/24/24 - Dewatering methods are being installed today. Once the creek water levels are lower, the existing culvert can be removed.

6/11/24 - Tree clearing is scheduled for today.

6/10/24 - Centerpoint will be installing the new gas line.

5/28/24 - Survey staking to begin.

5/2/24 - The contractor has provided their planned construction schedule, which can be found here County Ditch #58 Culvert Replacement Schedule.
The planned start date is June 3rd. The dates within the schedule are subject to change depending upon weather and contractor scheduling.

4/8/24 - Resident letters mailed with project details and contractor.

4/4/24 - The project was awarded to Northdale Construction at the April 1st City Council Meeting. The starting date has not yet been determined but will be updated as information becomes available.

Resident Notice Project Information
Approved Plans



 

 
The above information will be maintained as up to date as possible.