8/13/26 - The overlays are scheduled to begin Monday 8/17/26. The contractor plans to start in the Rosewood Addition Development which are the streets of 180th Lane and Ulysses Street.

7/20/26 - Project is planned to begin August 17th. Dan Hall from Bituminous Roadways is the project manager for this project. You may email him Dan Hall or contact him at (651) 686-7001.

A schedule for the overlays is located here Bituminous Overlay Schedule

2/10/26 - The City Council accepted the low bidder, Bituminous Roadways, Inc. for the 2026 Overlay at the January 20th Council Meeting. Plans can be viewed here: Approved Plans




 

 