2111 - East Frontage Road North of 171st Avenue
Lead Engineer : Luke Zellmer
E-mail: LZellmer@rfcengineering.com
(763) 862 - 8000

10/3/25 - Storm installation is wrapping up on the south end of the project and is progressing northward.

9/30/25 - Storm installation is being happening on the south end of the project and will progress its way northward.

9/25/25 - Muck Excavation has finished up and site grading will continue. Storm sewer installation will begin on the south side of the project on Monday 9/29/25.

9/11/25 - Site grading has begun on the south portion of the project. This includes stripping top soil and stockpiling it along with excavating of the ponds. Silt fence is being installed around the perimeter of the project and around wetlands.

9/5/25 - Tree clearing will begin today 9/5/25 and Saturday 9/6/25. Silt fence installation and site grading is scheduled to begin Monday 9/8/25.

8/27/25 - Tree clearing is scheduled to begin on Wednesday 9/3/25. Grading is scheduled to begin Monday 9/8/25.

8/19/25 - Surveyors will be on-site to mark out removals, silt fence, and the road centerline.

8/13/25 - The project is scheduled to begin 9/2/25. The proposed project schedule can be found here Proposed Project Schedule. Note that this is subject to change depending upon weather and Contractor scheduling.

7/29/25 - 2111 Resident Notice - Project Info have been sent out via mail to inform residents of the project.

7/23/25 - The project was awarded to A-1 Excavating LLC at the 7/21/25 City Council Meeting

6/18/25 - Bid Opening will be 7/9/25 at 11:00 AM. Council acceptance of lowest bid is planned for 7/21/25.

6/17/25 - The City Council approved the project to be advertised for contractor's bids.



Approved Plans



 

 
The above information will be maintained as up to date as possible.